Problem
The customer wants to be able to load a 1,000 ha survey and make designs of sections of this field (10 – 15 different fields) to take into account all the main field.
Solution
You can load 1000ha of survey data in OptiSurface, but I wouldn't advise it because the software gets bogged down for so much data, but I understand that he wants to design a whole farm effectively 15 fields at once.
You can design multiple boundaries in the same design file so you could potentially design different fields.
It can be done, but you will end up with a lot of data points depending on how intensely they surveyed. We generally recommend no more than 30,000 data points on one osd file.
Design for a 1000-Ha Field
Ed Foronda
Updated 6 months ago